title: Lean Construction Success | Boosting Panel Installation Productivity | Lean Enterprise Institute
description: See how Turner Construction crews raised panel install productivity 50%+ and cut a cable job from 239 to 24 minutes by redesigning the work. Free PDF.
image: https://info.lean.org/hubfs/Social-turner-case-study-pdf.jpg
---

[![logo-LEI-hubspot](https://info.lean.org/hs-fs/hubfs/logos%20and%20headers/logo-LEI-hubspot.jpg?width=300&height=90&name=logo-LEI-hubspot.jpg "logo-LEI-hubspot")](https://www.lean.org/)

Lean Construction Case Study

# Respect for People: Making the Job Easier for Workers

[![Cover of the LEI case study Respect for People: Making the Job Easier for Workers at Turner Construction](https://info.lean.org/hubfs/turner-case-study-cover-shadow.png "Cover of the LEI case study Respect for People: Making the Job Easier for Workers at Turner Construction")](https://www.lean.org/)

## Results on the Dallas job site

**50%+**  
higher productivity on exterior panel installation

**21 panels**  
installed in a single day, more than the crews had ever done

**239 to 24 minutes**  
to install eight cables after redesigning a hard-to-reach cabinet job

How Turner Construction crews used lean thinking to cut waiting, reduce physical strain, and install more panels with less effort.

The crews on a Dallas job site were already meeting their daily quota. After a week of coaching focused on how the work was actually done, they raised panel installation productivity by more than 50% and removed much of the physical strain from their jobs.

## Download your free copy

Get the full 11-page case study, including before-and-after diagrams of the panel installation and the complete 3C framework.

 

## What happened on the Dallas job site

The crews on a Dallas job site were already meeting their daily quota. So when LEI coach and Toyota veteran Bryant Sanders arrived to study how they installed exterior panels, people reasonably asked why they should change anything.

Then they looked closely at the work. One team attached channel to the building and rode the scaffold down. A second contractor rode up to install insulation and rode back down. Then the first team went back up to hang the panels. Most of the day went to waiting and riding, a sequence set by how the contracts were awarded rather than by anyone's choice.

After a week of job analysis, small experiments, and adjustments, panel installation productivity rose more than 50%. One day the crews installed 21 panels, more than they had ever done. On the same site, the team redesigned a hard-to-reach cable termination job and cut installation time for eight cables from 239 minutes to 24.

“We captured those guys’ hearts when we made that job so much less difficult.”  
Bryant Sanders, LEI

## What you’ll learn

- How the Turner teams redesigned panel installation so trade partners stopped waiting on each other
- The 3C framework Sanders adapted from Toyota to sort work by content, characteristics, and categories, so crews can spot cyclical, periodic, and abnormal work quickly
- Why lists of improvement ideas get ignored on job sites, and how gemba-based improvement puts resources behind changes right away
- How Turner and its trade partners share results across sites in San Antonio, Denver, and Dallas to win over skeptical crews
- What it takes to build lean thinking into contracts and requests for proposals before work begins

## Who it’s for

General contractors, trade partners, superintendents, project managers, and continuous improvement leaders in construction. Operations leaders outside construction will find the 3C framework applies to any work that is physically hard or easily disrupted.

## About the coach

Bryant Sanders spent 25 years at Toyota Motor North America in supplier development, quality, logistics, production operations, and Toyota Production System deployment. At LEI, he coaches operations leaders in manufacturing, healthcare, and construction.

## Frequently asked questions

### What does respect for people mean in lean construction?

In this case, it means treating sore hands, backs, and legs as problems to solve. Construction often treats physical strain as part of the job. Redesigning the work to remove that strain respects the people doing it and tends to raise productivity at the same time.

### What is the 3C framework?

A way to study work in detail by looking at its content (value-adding, waste, or necessary but non-value-adding), its characteristics (easy or difficult, overburdened, uneven), and its category (cyclical, periodic, or abnormal). It helps crews see where effort is lost.

### Who benefits financially from these improvements?

Mostly the trade partners. They bid work based on expected labor hours, so making the work easier or faster goes straight to their bottom line. The general contractor gains safety, reliability, and schedule adherence.